EAF revamp at BSW successfully completed.

On 26th January 2022 - one day ahead of schedule – EAF #1 started up successfully. Within 8 weeks the Badische Team has revamped the furnace completely. Within the first 24h of production, 29 heats were successfully tapped.

We want to congratulate the entire project team and are looking forward to an even more efficient and safe operation.